Project Description
REV 02: for the relocation of sanitary (SAN) and storm (STM) works at the Scarborough Health Network. Please refer to Revision C04 for details of the changes. Due to insufficient horizontal separation between the storm and sanitary sewers (only 70 cm), installing two separate manholes was not possible.so MH 18 is now proposed as a dual manhole.Revision 01 - relocation of the sanitary and storm works at the SHN (Scarborough Health Network- General Hospital) for the SSEThe existing 250 - 300MMØ SAN and 300-400MMØ STM near the CKD building are currently in conflict with the SOE footprint. In this scope, these pipes will be re-routed to the north running along the west D-Wall and be connected to ex. SAN and STM lines running along McCowan
Permit Details
| Permit Type | Drain and Site Service |
| Work Type | Site Service |
| Structure Type | Other |
| Revision | 02 |
| Ward | E2130 |
| Builder/Owner | N/A |