Data provided by open.toronto.ca
Building Permit
24 115877 STS
Inspection
532 BAY ST
Applied Jul 6, 2015
Project Description
The proposed work is within the Toronto Hydro's Transformer Station. Hydro One is installing a utility tunnel to replace their aging high voltage transmission cable and an access shaft will be housed within the transformer station. To accomodate the installation of the access shaft, the existing storm sewer piping needed to be realigned.
Permit Details
| Permit Type | Drain and Site Service |
| Work Type | Site Service |
| Structure Type | Other |
| Revision | 00 |
| Ward | S1025 |
| Builder/Owner | N/A |