Data provided by open.toronto.ca
Building Permit
22 241446 HVA
Inspection
300 HUMBER COLLEGE BLVD
Applied Mar 7, 2025
Project Description
Revision 01: A summery of changes are as follows: "Flour bin platform" renamed to "dispensing bowl platform and has changed locations as well as design changes, addition of platform within blower room for inspection of equipment, roof reinforcing design for the addition on RTU's. All changes are clouded within the attached drawing.HVAC - Phase 1 - Construct a blower room, sifter room, extend a mechanical storage mezzanine, construct one office. Phase 2 - Install a flower & sugar silo, associated delivery system, mezzanine to support indoor bin & hoppers
Permit Details
| Permit Type | Mechanical(MS) |
| Work Type | Building Permit Related(MS) |
| Structure Type | Industrial Processing Plant |
| Revision | 01 |
| Ward | W0121 |
| Builder/Owner | N/A |