Data provided by open.toronto.ca
Building Permit
18 237788 FND
Permit Issued
11 CENTRE AVE
Applied Oct 22, 2025
Issued Dec 17, 2025
Project Description
Conditional Permit - Construction of New Toronto Courthouse, a new 17 Storey Modernized institution, incluing 63 new courtrooms, a public atrium, new public realm, prisoner handling area on the B1 level, and private judicial parking on the B2 level. Integration of heritage and indigenous elements with an enhanced accessibiltiy program throughout the building. It is anticipated that this courthouse will be built to a LEED silver status.Part Permit -
Permit Details
| Permit Type | Conditional Permit |
| Work Type | Partial Permit - Foundation |
| Structure Type | Multiple Use/Non Residential |
| Revision | 00 |
| Ward | S1025 |
| Builder/Owner | N/A |