Project Description

Plumbing - Basement Boiler Room: replace existing door, extend landing including stairs, demolish existing and construct new concrete housekeeping pads, and install new containment curb.Basement Standby Power Room: demolish existing and provide new concrete housekeeping pads.3rd Floor Storage Room: construct new wall to separate room into two, provide new door for each room, install new domestic cold water line, drain, ventilation and containment curb in new M&E Room.

Permit Details

Permit TypePlumbing(PS)
Work TypeBuilding Permit Related(PS)
Structure TypeOffice
Revision00
WardN1825