Data provided by open.toronto.ca

Building Permit

16 157105 PLB

Permit Issued
130 THE QUEENSWAY
Applied Dec 17, 2025
Issued Dec 31, 2025

Project Description

Rev 01: Revision to use trap guard in lieu of trap seal primer.Plumbing - upgrades to existing west substation and construct concrete pads for transformers. News fans and heaters within building.

Permit Details

Permit TypePlumbing(PS)
Work TypeBuilding Permit Related(PS)
Structure TypeIndustrial
Revision01
WardW0329
Builder/OwnerN/A