Revision # 04 - Regarding green roof coverage. The additional minor variation in coverage is due to as-built conditions. Additional paver is required for tenant mechanical units and base building fan equipment access. Portion of the green roof is also removed to accommodate BMU platform and rotating bumper rollers.REVISION 3 - changes to interior glass walls on Level 41Proposal to construct a (39 levels of offices + 3 levels of mechanical spaces; level 13 is skipped on all drawings) 42 sty office building with 5 levels of below grade parking.
Permit Details
| Permit Type | New Building |
| Work Type | New Building |
| Structure Type | Office |
| Revision | 04 |
| Ward | S1031 |
| Builder/Owner | N/A |